All of the drywall is hung on the main floor and garage. Tomorrow the drywall will be hung in the basement, then the taping and coating can begin. Vic is awesome, he did a great job and was fast.
Stydinger was out and back filled our trench before all of the rain came and washed away our stone dust again. Hopefully if it stops raining, we will have electric by the end of the week. Stydinger will come back next week to install the septic. The septic pipe entry hole is not in the right place so we will need to drill another hole and fill the existing hole with concrete and waterproofing before the ground is back filled back in around the house.
Siding has been put on hold briefly since it has been raining so much. Bill has been getting the lines in the electric panel hooked up and ready for electric before it is hot/active. He is not too far off from finishing this task.
Tuesday, October 23, 2007